# Sizing a microgrid PCS: load, starting surges, generator and transformer capacity

Start with simultaneous load, check surge magnitude and duration, then review generator headroom, transformer loading and battery limits. One kW figure cannot settle PCS sizing.

Concept illustration for this topic, not an actual project, equipment wiring diagram or approved system configuration.

A customer’s total power figure starts the discussion. It does not finish it. The equipment running together, the hardest starting event and the operating roles of the generator and transformer need to be assessed together.

1. Separate installed load from the load the PCS must carry

List electrical input power, operating hours and starting sequence. A motor nameplate may state shaft output; account for efficiency before comparing it with electrical input. Installed nameplate totals, simultaneous demand and essential backup load are different figures.

Full-site backup must support the agreed production condition. Essential-load backup needs its own circuit list. Do not invent a diversity factor to fit a smaller inverter. Add confirmed expansion and justify a continuous-power allowance; 20% is not a universal rule.

2. Check starting events separately from continuous headroom

Pumps, compressors, lifting equipment and transformer energization may set the limit. Obtain starting current or kVA, duration, the load already running and acceptable voltage/frequency disturbance. Direct-on-line, soft-start and variable-speed operation need different evidence.

Compare the event against a documented PCS current-versus-time capability for the relevant voltage, temperature and mode. A brief peak claim does not establish that a motor can start for several seconds. Review sequencing or a suitable starting method before increasing capacity; neither is an automatic cure.

[Cummins T-030 · 3.3](https://www.cummins.com/sites/default/files/2024-08/t030-Liquid-cooled-gen-set-application-manual.pdf)

3. Establish what the diesel generator can actually supply

Record kW, kVA, power factor, voltage and the applicable PRP, LTP or other duty rating. Check permitted operation and site derating. Do not convert duty categories with a fixed percentage.

When the generator feeds loads and charges the battery, budget the concurrent AC load, AC-side charging input, relevant losses and headroom. Confirm transient response, input compatibility and charging controls.

Adding PCS and generator nameplates is valid neither as a design nor as proof of surge support: approved synchronization, load sharing and protection are required. With an ATS selecting grid or generator, the two sources are not simultaneous capacity. A 200 kW generator does not automatically require a 200 kW PCS.

4. Locate the transformer and check kVA

Review its rating, voltage, current, impedance, connections and existing loading. For one operating condition, S≈P/PF is an initial check. Mixed loads require real/reactive power or measured-current assessment; do not assume every load has PF 0.8 or 1.

A transformer in the PCS-to-load path must carry that power flow. A utility entrance transformer instead constrains grid exchange and charging; it need not limit all local islanded output. Avoid counting existing demand twice.

If the PCS must energize the transformer during black start, obtain design-specific inrush data and check the starting method and PCS current limit. A 315 kVA nameplate is not an instruction to select a 315 kW inverter.

[kW / kVA](https://www.electrical-installation.org/enwiki/Installed_apparent_power_(kVA)) · [FA102519](https://www.se.com/us/en/faqs/FA102519/)

5. A worked screening example

These are teaching assumptions, not VGRID ratings or a recorded project. Simultaneous load is 90 kW, confirmed expansion 10 kW, assumed PF 0.85 and a project-specific 20% continuous allowance. The initial requirement is (90+10)×1.20=120 kW, about 141.2 kVA.

Suppose a measured starting event needs 210 kVA for 3 seconds. A 150 kVA continuous candidate does not pass merely because 150 exceeds 141.2: its 120 kW capability, short-time current, three-second duration and voltage performance all need confirmation.

Suppose the generator’s applicable rating is 250 kVA/200 kW. A 90 kW AC load plus 40 kW of AC-side charging input totals 130 kW for an initial active-power screen. This does not validate kVA, transient behavior, ambient limits or controls.

If a 315 kVA entrance transformer already carries 240 kVA, adding charging assumed near 40 kVA gives a conservative arithmetic screen near 280 kVA. Then check P/Q, phase currents and heating; do not add demand already included in 240 twice. Islanded energization is a separate case.

6. Check the battery and DC path

Minimum operating voltage, battery/BMS current limits, SOC, temperature, DC wiring, protection and PCS derating can limit available output. Battery kWh establishes energy, not proof of sufficient kW.

PV-controller power is not AC inverter output. LEONA-M200K performs PV-side MPPT DC conversion; its 200 kW cannot simply be added as PCS power available to AC loads.

7. Bring a complete design brief

Provide a single-line diagram, full-site and essential-load lists, measured load profile, motor starting data, generator and transformer nameplates/test data, battery/BMS limits and expansion plans. Identify parallel operation and black-start requirements; mark missing evidence clearly.

The VGRID assessment form offers an initial power-class candidate. Final selection must pass continuous kW and kVA, starting events, generator operation, transformer constraints and battery capability. None of those nameplates is a substitute for the full check.

[Complete the project assessment](/en/blog/category/guides#assessment-form)

References and scope

These references support general sizing principles, not VGRID overload or parallel-operation ratings. Accessed 2026-11-12.

[Cummins T-030, Issue 9 (02-2015), chapter 3](https://www.cummins.com/sites/default/files/2024-08/t030-Liquid-cooled-gen-set-application-manual.pdf)

[Schneider Electric — Installed apparent power (kVA)](https://www.electrical-installation.org/enwiki/Installed_apparent_power_(kVA))

[Schneider Electric — Transformer inrush, FA102519](https://www.se.com/us/en/faqs/FA102519/)

## How do you size a microgrid PCS: total nameplate power or simultaneous demand?

Not from that sum alone. Establish simultaneous demand, essential backup loads and confirmed expansion, then check kW, kVA, power factor and site derating. Do not invent a diversity factor.

## Will 20% inverter power headroom cover motor startup?

Not necessarily. The article uses 20% only as a teaching assumption for continuous headroom. Starting current or kVA, duration and voltage disturbance must separately match the candidate PCS overload curve under the relevant conditions.

## Does a 200 kW generator require a 200 kW PCS?

No fixed match applies. Check the applicable duty rating, site-available output, concurrent loads and charging input. Combined operation needs approved synchronization, sharing and protection; ATS-selected sources cannot be counted as simultaneous supply.

## Does a 315 kVA transformer call for a 315 kW inverter?

No. Distinguish kVA from kW using power factor, and review transformer location, existing loads and power flow. An output-path transformer and a utility entrance transformer impose different constraints; black-start inrush is a separate check.

## Does a 150 kVA candidate pass because the example needs 141.2 kVA?

No. The example also requires 120 kW continuous capability and assumes a 210 kVA starting event lasting 3 seconds. Active power, apparent power, short-time current, duration and voltage performance all need verification.

## Can battery kWh or MPPT kW replace the PCS power rating?

No. kWh is energy, while battery/BMS current and minimum voltage also constrain output. An MPPT controller converts PV-side DC; its rating is not directly available PCS power for AC loads.